59-61 ONLSOW GARDENS, SW7

Project: External repairs and decorations
Client: Shaw & Company Chartered Surveyors
Contract: JCT MW

We were engaged to carry out cyclical external repairs and decorations to the front and rear of the property. Full height alarmed scaffolding was required to facilitate works.

Works to the common parts included:

– Façade repairs using Tourpret Murex
– Window Care Repairs using Dry Flex 4
– 3-coat render repairs
– Brickwork cleaning
– Cold applied flat roof coatings
– Decorations using Wellcome Trust approved Dacrylate
– Specialist signwriting to front columns

Works were completed within 10 weeks of the contracted 12-week programme, receiving high praise from the client and CA.